“Keir International proud to have energized S/S for Diriyah Gate Development Authority (DGDA)
Last Friday, 9 March 2022.”

Diriyah Gate Development Authority – Utility Execution Project is a strategic project executed by Keir International for such a VVIP customer.

The project scope include:

  • Permanent power delivery to Diriyah Gate Development Authority.
  • NWC water connection to headquarter office.
  • NWC sewage permanent connection to headquarter office.

Project was undertaken for a short time for 6 months as a targeted period to change over on a running systems from temporarily connection and generators to permeant connection. Keir commitment with skilled and professional engineers could deliver the project with best quality and time.

This project was running 24 hours a day, 7 days a week. It required a continuous work and plans a head to commission a new connection system from DGDA temporary generators to Saudi Electricity System through a new built in system.

This system contains transformer, RMU, Low Voltage Panels, Automatic Transfer Switches, & connection to existing systems.

The integration process was a good quality with an interruption time for 15 minutes.

Water scope has new underground tanks with several water pumps & a new connections with manholes to connect to NWC swage system.